Building my 26’ Norwalk Island Sharpie by
Klaus Sussenbach
Part 2,
the building process:
The
materials list which came with the plans needs to be changed if the boat is
going to be modified in any way. Even with my extensive modifications I used less
plywood than I had expected, some of the left over sheets were later used to
build a stitch and glue dinghy.
For the
sharpie I used the following plywood, all 8x4’ sheets:
1sheet 12mm
okoume marine plywood
27
sheets 9mm -.-
2
sheets 6mm -.-
8
sheets 4mm -.-
8
sheets 12mm hoop pine marine plywood
2
sheets 6mm -.-
1
sheet 3mm -.-
It pays
to order all the plywood at once as there are quantity discount and transport
cost savings. This also applies to the epoxy resin. Most of the other materials
were bought as they were required. I kept looking for boating gear specials at
boat shows etc. and purchased many items which were only required at fit out
time. Leave electronic items until last, it outdates too quickly. This way, by
the time the hull was completed I had accumulated most of the hardware,
spreading this considerable expense over a long period.
I also purchased the mast and booms early in
the process of building the boat and often took to rigging them while waiting
for the epoxy to go hard. Think carefully before drilling holes into these,
some areas are under high stress and some fittings need to wait for
installation until you have the sails to get their exact location.
For the
solid timber a variety, locally available, was used, including teak, jarrah,
kauri pine, western red cedar, douglas fir, and american white ash.
Don’t
worry if you cannot find the required lengths of clear solid timber as these
can easily be scarfed from shorter pieces.
How
much did it all cost?
Rather
than boring you with what the finished boat cost me I calculated the
percentages where the money went. This is for a complete boat, on a trailer, ready to go cruising (just add food
and fuel).
The biggest
item at 24.5% was the 1000’s of miscellaneous things that go into a boat such
as hardware, rigging, ropes, blocks, sheaves, electrical items, plumbing, nuts,
screws, bolts, fittings etc. etc.
Next
with 15% came all the plywood and solid timber used.
Then at
12% came the sails, comprising of the main, mizzen and staysail.
Followed
by 10.5% was the epoxy (I used 100 litres), glass cloth & tape, fillers,
graphite, measuring pumps etc.
The
cost of the home built trailer amounted to 8% of the total.
The mast
and boom extrusions (aluminium) took 7.5 %.
Major
electronics (including autohelm, 27Mhz radio, log, depth sounder and Honda
battery charger) were 6.5%.
Outboard
motor & fuel tanks, 6%.
Safety
gear, 3%.
Paint,
varnish, brushes, rollers etc., 2%.
Boat bunk
cushions and covers, 2%.
Lead
for ballast, 1.5%.
Labour
for welding of stainless and aluminium fittings and parts, 1.5%
That
should give you some idea where the money goes and where you might save some
should you wish to build a less elaborate boat. Please remember that these are rough figures which apply to my
location and may be not comparable elsewhere.
For the
building, a number of homemade items came in very useful, they were:
Circle
guides, I wrote down every small radius on the plans and cut a circle for this
out of scrap 3mm perspex pieces, with a flying cutter. This gizmo may be known
by a different name, it has a shaft to
fit into a drill chuck on which is a 6mm pilot drill bit and an adjustable arm
with a downward facing cutting blade. Make sure the blade is set for disk
cutting rather than for hole cutting. You can use this only on a pedestal drill
with the perspex firmly supported, cut through half of the thickness from each
side to avoid cracking of the perspex and take care! I also cut out many
smaller size disks down to 20mm diameter and ended up with a stack of disks. It
was much easier and quicker to lay a
disk on the appropriate spot on the plywood and draw the required circle
segment than using a compass would have been.
A
straight flat batten, slightly longer than the largest cabin top curve radius,
on one end of which a small hole to hold a nail was drilled. From this hole I
marked the required radius towards the other end of the batten and drilled a
further hole to just fit the tip of a pencil. To use, tap the nail in at the
fulcrum and use the batten as a very long compass to draw the curve section. To
avoid wasting plywood, as this fulcrum often falls outside the sheet, you need
to slip another sheet under it which has a centre line on it. Line this up with
your first sheet and draw the curve section. I did all this on the floor with
weights on the sheets to stop things moving out of alignment.
It pays
to consider carefully how the bulkheads are cut out of the ply sheets and how
to use the off cuts for smaller items, its there were the savings in plywood
sheet numbers come from.
As the
narrow sections across the top and bottom of the bulkheads are trebled, for my
boat I cut some of the bulkheads from sheets butted onto each other while
drawing the shape, giving me a port and starboard half, the butt being the
centre line. It is important to line resulting the halves up carefully when
gluing on the doublers to have a smooth cabin top curve. Experiment a little to
minimise wastage, its easy to rub out a pencil line and mark again.
A
clamping jig for the many scarf joins on the long solid timber pieces. This was
made from 2 lengths of 50x50x3mm (2”x2”x1/8”) angle iron and a piece of flat
bar, 100x5mm (4”x3/16”), all about 1.8m (6’) long. The angle irons were bolted
to each side of the flat bar to form a “+” cross section, the bolts all in the
lower section of the ”+”. This gave two right angles to line up the scarfes for
gluing, it allowed the gluing of two
scarf joins simultaneously. Cover the gluing surfaces with plastic packing tape
to prevent the epoxy sticking there. To use it I clamped the jig into a vice,
placed the timber pieces on the covered section, gluing face up and applied the
epoxy to both surfaces. Always apply a straight epoxy coat first, let it soak
in, reapply more until surface remains wet, then mix in the thickening compound
and apply to both surfaces. Flip the pieces on one end of the jig over so that
the thin edge of the scarf is against the flat bar and clamp them to it. Then
flip one the other pieces over, line up the scarf and carefully clamp down to
the angle iron, making sure it does not move sideways. Repeat for the last
piece, then place clamps across the scarf area and along the jig length to keep
all tucked tight into the corners and lined up straight. Do a dry run for the
first time to get it all worked out without the messy epoxy.
For the
scarfing on the jig above and for other jobs a couple of adjustable stands come
in very handy. I made mine from an old plough disk as a base, welded on a
vertical tube in the centre and had another tube telescoping into this, locked
by a screw knob. The top of the smaller tube had a cross piece welded on where
I fitted a roller. This roller is for using the stand with the bandsaw or table
saw but not needed if you don’t have these machines.
I made
4 sturdy saw horses from hardwood, very useful
to work along the hull later. I also had two stools of half the
sawhorses height, again very useful.
Long boards
are also required, known as “torture boards” in these parts, I had a 900mm (3’)
long one and two 600mm (2’) long ones which had different thickness bases to
bend to the hull curvature. The longer one was more tiring to use but faired
the better in most places. Its important to have comfortable handles on them to
reduce fatigue, you’ll be swinging them for hours on end. I bought the 100mm
wide (4”) sandpaper for them in 50m rolls, one of 80 grade and one 120 grade,
its much cheaper than buying by the metre and it all was used up. The handles
on my boards (mushroom shape) had a groove in their bases to clamp the sanding
paper over a matched bump on the board. I undid two wing nuts, placed the paper
ends under the handle bases and clamped them back on to hold the paper firm.
All
this sanding makes a lot of dust which is not healthy to breathe in. I am a
wearer of glasses and have a beard and this made using disposable dust masks
useless for me. I purchased one of the hood type masks with face shield which
completely cover the head. These have a tube emerging from the back of the hood
which normally connects to a filtered air pump, worn on the belt, to supply
clean air to the wearer. Unfortunately this pump was very expensive, so I came
up with the following alternative:
A new
pool hose, 9 metres long, was purchased and one end adapted to fit the short
hose from the hood, this pool hose is inexpensive and flexible enough to pull
easily behind oneself. The other end of the hose terminated in a box I made up
of scrap wood. This box housed a 3 blade mains powered fan I’d salvaged from
somewhere, the air intake had flyscreen placed across it. The pool hose plugged
into a PVC fitting I got from the plumbing supply store, this was screwed into
the back of the fan box.
Now, the clever bit. I mounted the fan box
against the window to draw in fresh air from outside and blocked the rest of
the window off. When wearing this contraption one gets continually supplied
with clean, cool outside air, great to dry away the sweat produced by a unfit
boat builder! I tied off the pool hose end at my belt to keep it from
separating from the hood hose as I moved about the boat.
On to
the building sequence:
I did
not follow the instructions on the plans there but rather followed a sequence
suitable for my modifications.
The
first item I made for the boat was the rudder blade (the building shed was not
ready yet), this was made from laminated staves of alternating red cedar and
douglas fir, a strip of white ash were the pivot bolt went through and jarrah
hardwood strips for the leading and trailing edge. I used the router method of
shaping the board after making a router guide from computer generated foil
templates. This method produces the very best symmetrical finish and is not particular
difficult to do. My rudder blade has the bottom corners rounded off rather than
the elliptical shape shown on the plan as this was easier to do.
Next
was the centreboard, as this is quite large I bolted a firm 2.4m (8’) long
panel on top of my workbench to make a large flat space for it. As the centre
board is tapered, the routing jig like as used on the rudder blade could not be
used (it only works on parallel sided boards.
I made
another routing jig which shapes the board length wise as against the cross
wise routing of the rudder blade. This worked very well and was easy to do.
On the
CB, because of its large size, the wider and thicker staves used, the
laminating is done on a 6mm thick marine plywood backing, cut to the board
size. Actually, I cut the trailing edge 25mm narrower to later glue on a
hardwood strip to avoid having the finished thin trailing edge of the board in
the plywood.
The
timbers used were jarrah (a local dense hardwood with good marine qualities)
and douglas fir, in alternating staves, all glued to the plywood base. I used
jarrah for the leading, trailing, top and bottom edges and also a piece which
had the recess for the lifting sheaves already cut out.
It is important to clamp the staves firmly to
the table top base as well if they have any slight bend or this bend is later
present in the finished product!
I borrowed some sash clamps and also used my
tube clamps for this job.
When I
tried to move the completed board blank I could barely shift it, it weighed
50kg!
And that was only half the board!
There was no way I could see myself moving
and turning the large, unwieldy finished laminate about to router out the
profile.
Then I
had the inspiration: why not make this centreboard as two halves, a port and
starboard CB so to speak, both in the same case.
In case
this idea did not work it would not be difficult to screw the board halves
together and fair the gap later.
And so it came to pass that my boat sports these
fancy assymetric CB’s and they work very well in the bargain.
Once
the board halves were shaped to the final profile I calculated that the
buoyancy of the submersed volume is about 7kg, in other words, the board would
float, which is something to be expected of a wooden board even if it was
heavy.
I then cut the leading lower corner of each
half board off on the diagonal with my bandsaw and took the off cuts to the
foundry after gluing on a 6mm thick plywood slice to allow for the loss of
material at the saw cut and the expected shrinkage. The foundry cast these
shapes in lead alloyed with a little
antimony to make it tougher. The lead corner pieces were attached with 1/4” ss
allthread pieces, threaded into the lead and inserted into epoxy filled holes
in the board. The gluing face of the lead was first sanded through the wet
epoxy to roughen it and remove the surface oxide layer for a good bond and the
pieces were then epoxied in place to make the boards whole again. The board
halves were then glassed all over with 10oz glass, the final coats saturated
with graphite powder. The rudder blade also was glassed over and received a
graphite coating.
The lead pieces weighed in at 15kg each,
sufficient to make the centre board sink but not too heavy for the lifting
tackle.
Originally
I fitted a 3: 1 purchase for each board half, this needed too much muscle to
raise the board easily so it was later increased to a 5:1 purchase by the
fitting of more sheaves.
I was
not 100% sure if the boards would sink if the lifting rope was let go as the CB
case and pin were a snug, rattle free fit. So I attached a webbing belt to the
leading edges to attach a lowering tackle if required. This was indeed later
used, with a 3:1 purchase, to tug on it a little to start the board moving
down.
There
are plastic flaps over the wide (100mm, 4”) CB slot, to close it off after the
board has exited, this reduces turbulence there to the point where it cannot be
observed from the top of the CB case. These flaps are held with 25x3mm ss
strips, recessed and screwed on each side. It is important that these flaps,
starting at the width of each board forward, overlap aft to each cover
completely across the slot.
If this overlap is too narrow the flap will
curl up and jam the board when raising
it, be warned.
I sourced the plastic strips I used from cold
room strip door material, they work well.
The
next project was the CB case, this had 9mm okoume ply sides, if I did it again
I would use the denser hoop pine ply there for peace of mind. The diagonal
stiffeners were from jarrah, as were the solid cleats along on each side on the
bottom. These cleats need to be shaped to follow the bottom curve. The top of
the case was made in teak, varnished bright with the sloping top section
removable to access the lifting tackle. I also made provision to lock the
boards up for trailering (and take the load off the lifting sheaves) by
inserting a 3/8” ss rod through ss strips inserted into the board tops.
The lifting tackles exit aft under the
outside companion step through deadeyes, then down in the centre of the sloping
cockpit floor to a set of sheaves under the thwart, thence to cleat off at
angled clam cleats fitted on the aft face of the thwart. It is easy to operate
the CB’s from the cockpit.
The CB
pivot pin was initially 1/2” ss but I had to increase this to a 5/8” ss rod as
the smaller diameter rod actually bent
slightly (this may have happened after the board kicked up while once
passing too close over a reef, thanks for pivoting boards!)
With
the CB, its case and the rudder blade out of the way, the boatshed finished,
the boat building could proceed in earnest. First, all plywood sheets received
a soaking coat of epoxy, thinned with TPRDA, then another coat which was sanded
with a random orbital sander.
This job is easiest done while the whole
building floor is available to set up tables and trestles and do a number of
sheets at a time. Its really the easiest way to totally cover all the plywood
with epoxy, the pre coated sheets also give a cleaner cut from the jigsaw
(sabre saw) with less splintering on the cutting line.
The
bulkheads came next, I tried to pre finish them as much as possible (there are
no epoxy runs on a horizontal surface)
and fit all the cleats for the furniture. In retrospect I should have fitted
only the cleats to one side, opposite of where the supports from the building
frame go, as some of the cleats got in the way there later.
For
cleats I used a triangular cross section of western red cedar, made by ripping
(25x25mm, 1”x1”) stock diagonally. They are just as strong but half the weight
than square ones and you get twice as many out of a length of wood. They are
also easy to plane and sand to any required bevel.
I bought a heap of leftover cedar from a
house builder cheaply, these were varying length planks and they had heaps of
knots. After ripping them to size, there were lots of useful lengths between
the knots as most cleats used in the boat were shortish anyway.
I must have used hundreds of metres of
cleats, its amazing how they disappear into the construction.
Clamping these triangular pieces was no
problem, I made a dozen short pieces of wood with a matching cut out to fit
over the angular edge when applying the clamps.
Since I
had so much cleating material I fitted these on both sides of all joins, making
for a very strong construction. I used no epoxy fillets anywhere inside my
boat, all was done with these triangular cleats.
About
gluing bits onto bulkheads and gluing generally, often it is not possible to use
clamps as they cannot reach the desired spot. I used lead weights, made from
200mm lengths of 25x50mm RHS
(rectangular hollow steel) filled with lead, about eight of these. Also smaller
ones of 20x20mm RHS, a dozen of these. Then there were lead ingots made by
casting lead into a 300mm long section of steel channel, 50x100mm, with welded
up ends. These weighed 15kg each, I had six of these. All these weights came in very handy.
The
ballast weight slabs were also home poured into a steel channel, I made those
to be of 50kg weight as I could not handle anything heavier by myself. The
ballast bolts were cast in, these I made from 1/2” ss allthread sections with a
T crossbar welded on. The lead pouring is a story by itself, not difficult but
can it be dangerous, send me an email if you want the details.
The
blkhd A was made from 2 layers of 6mm hoop pine ply, this way it was easy to
make a lip for the centre opening cover. This cover was made from the cut outs
by carefully cutting with a jig saw and using a row of small holes for the
start of the cut.
The
transom was also laminated from 2 layers of 6mm okoume ply to get the desired
curve at its top edge, it also had the laminated top beam and curved aft face
of the motor well fitted on already.
At this
stage it is also advisable to consider just where the wiring and plumbing runs
past the bulkheads and drill the appropriate holes into them as these might be
difficult to drill later. I used the outboard side of the carlins to run my
wiring, a white 25x25mm ducting with snap on lid is screwed on there, making
the wiring invisible from the cabin yet for it to be accessible and reach
everywhere. To this end there were 20mm holes drilled through the blkhds,
outboard of the carlin notches, easy to do at this stage but very difficult
later in the building process. I had to elongate some of these holes later with
a file as there were more wires than I thought to go through them!
Now it
was time to assembly the building frame. I strung a length of piano wire, through
notches at the bottom of the building frame cross members, along the centre
line. This wire was carefully levelled and tension applied by means of eye
bolts at each end to have no sag along its length. This was the reference line
against which everything was lined up.
The building frame, made of heavy 150x50 timber was also bolted to the concrete
floor to make it unmovable.
I
installed the blkhds at their marked
locations on the building frame, (take care from which side of them you measure this!), using the method described
in Kirby’s plans.
If I did this again I would also cross brace the blkhds from
the roof rafters, making a much more secure 3 point fixing. The blkhds, on
their two temporary legs, are quite wobbly and want to move about when the chine
logs are bent around later. You may also have to temporary clamp or screw
stiffener logs across the blkhd openings to avoid distortion on some of them
during this process.
Once
the bklhds were located in position and all measurements crosschecked about 3
times, the chine and sheer logs can be fitted. The dimensions specified for
these makes it very difficult to
bend these around in one piece, laminating as suggested by cutting into inner
and outer half also is troublesome because they have to bend both ways. I made
mine up by laminating them from upper and lower halves, these, being almost
square, bend easily in both directions. I also got less waste this way as I cut
these strips from planks of kauri pine.
These
planks were only 3.6m (12’) long so 3 strip
sections were scarved end to end to make up the full length. The lengths
were later installed offset to place the scarf joins at a different place on
the complete laminate. Make sure these pieces overhang the hull by about 0.5m
(2’) aft and 0.25m(1’) forward to make a fair curve and you got something to
pull against. I scarfed up all the pieces required for the 4 chine log and 4 sheer clamp lengths at
once, using the jig described earlier. These were stored on a shelf until
needed.
When
cutting the notches in the blkhds for these logs it pays to cut them smaller
than shown on the plan initially as some have a far bit of a bevel. You also
need to allow for the topside bevels when gluing on the bulkhead doublers here.
Use one of the scarfed lengths as a batten to bend around the notches and mark
the bevels. Once these have been adjusted glue some extra large cleats on
either side of the blkhd notches which do not have doublers there to accept the
screws holding the chine and sheer logs until the epoxy cures, these of course
also need to be bevelled. The blkhd itself is too thin there to hold screws.
Then I
installed the temporary fore and aft blkhd which holds the stem in its place.
The precise location of where the laminated logs meet the stem were marked on
this blkhd. The stem for my boat was laminated from douglas fir and white ash
and screwed to the temporary fore and aft blkhd with small brackets.
Now came the tricky job of marking and
cutting the notches for the chine logs and sheer clamps into the stem, I did
this a little bit at a time, using the scarfed length batten to get the bevels
right, it was not an easy job as everything comes to a point here. The forward
ends of the chine log and sheer clamp were tapered too as the stem is not fat enough
to accept their full thickness. I also fitted a stout, laminated, knee to the
chine log / stem joint as this area looked a bit weak to me.
Take your time and work with care, this joint
takes the brunt of any collision with floating hazards!
To install
the chine logs, choose one side and
dryfit and screw the log in place to the notch corners of the bulkheads,
starting in the middle and working fore and aft until you are satisfied all
fits in place and runs a fair curve. Stand back and sight along the entire boat
to make sure!
Mark the glue lines with pencil on the blkhds
and logs. Disassemble and coat with epoxy all the log surfaces facing the
inside the boat, leaving the marked gluing places dry. I chamfered the inner
corners of these logs for a pleasing look using a power plane. The chamfer just
runs out before each of the blkhds. Do this also for the other side. When you
have done this you can start gluing
these logs in place. It’s a bit tricky to handle these long snaking bits of
wood without smearing epoxy everywhere but can be done if some temporary
supports are clamped to the blkhds. Start at Blkhd E and work both ways,
driving the screws back into the holes from the dry fitting stage. Then do the
opposite side of the boat with your next log to avoid distortion of the blkhds.
When
all of the chine log and sheer clamp halves have been glued in place in this
manner you may remove the screws or simply leave them there if they were countersink
stainless screws. Clean out the squeezed out epoxy from the remaining notch
areas and dry install the other halves of the laminate as before. You can now
use clamps to clamp them to the existing log halves as well to follow the exact
same curve, mark and pre coat inside surfaces as before. Then you need to glue
the entire length of the mating surfaces and the notches all at once, use the
screws as well as clamps to hold everything in place until all is cured. This
operation is a bit tricky to do but if thought it out well there should be no
problem. I used about 20 clamps for this process, if you don’t have that many
borrow some before you mix the epoxy L.
Here I should pass on another trick which
made cleaning up epoxy squeeze out much easier. Initially I used a chisel
to scrape off the excess but this had to be done after a certain curing time
while the epoxy was still soft which often coincided with my sleeping time.
Someone on the rec.boats.building newsgroup mentioned a heat gun to soften the
epoxy and scrape it off, it works like a charm!
You
need an electric heat gun with a rather small nozzle (1/4” diameter approx.) I
use a Leister heat gun, but others also will do as long they have a heat
control to limit the nozzle temperature to less than 200 degrees Celsius. You
can always drill some bleed holes into the nozzle if it is too hot, the epoxy
surface must not char if the nozzle is held stationary for a few seconds.
I also found a blunt chisel useful there, just heat the epoxy bead with the nozzle
and follow with the chisel to lift the softened excess epoxy off without
cutting into the wood. At corners I used a gauge to get a small radius finish
like a tiny fillet. There is almost no sanding required with this process and
consequently no dust.
The
next job will be to install the CB trunk, it’s a big, unwieldy, thing and I
rigged some tackles from the ceiling to suspend and lower it in place. Another
reason why you need a high ceiling in your building shed.
Dry fit everything and mark where the epoxy
glue goes. The first bottom layer of ply butts against the trunk sides in my
boat so the trunk stood proud of the bulkheads by 12mm at this stage. The
tackles were used to raise the thing
for application of the epoxy then it was lowered and clamped in place where
clamping was possible. Place spreader pieces into the CB slot to avoid it being
squashed inward and have consequently a difficult fit of the CB later.
Now the
hull has taken on a shape resembling the boat, I then decided to fit as much of
the interior fittings while the sides and the bottom were still off for easy
access.
This
comprised of all the vertical panels, such as bunk fronts, cockpit sides and
floor stiffener etc. These were first dry fitted to their appropriate cleats
and marked, then I applied the final epoxy coat on the bench and two coats of
white primer before gluing them in place.
A note
about painting the interior: it was very apparent from the nearly finished hull
I had seen before I started on mine that it would be difficult, messy and in
some places impossible to paint some areas inside of the boat if these were
left until the hull was complete.
So I
applied two coats of white undercoat paint to
all interior surfaces on top
of the epoxy coats which were not left bright and varnished later, prior to
gluing them in place. There the later inaccessible or difficult to get to
surfaces received a final coat of white gloss paint (I used interior marine
paint).
My
reason for painting in addition to the epoxy coat is: it is much easier to spot
holidays (missed parts) in the white paint cover than in the epoxy coating, any
such places got additional covering and the light colour makes it much easier
to see small things in lockers and such. And I don’t have to worry about condensation
encouraging wood rot at some hidden away place.
It may
look like slowing up the building process when painting everything before
installing it into the hull but it sure is much easier to do at this stage.
The
cockpit floor has a vertical fore and aft stiffening panel under its centre,
running from the aft face of the CB case to blkhd G and another one between
blkhd G and H. These panels had large circles cut out to lighten them and allow
the ventilation of the buoyancy chambers if their ports are opened. I think
this modification is essential to bear the weight of the crew standing in the
cockpit.
On the
aft face of blkhd C and forward face of blkhd F I fitted ss chainplates under the side deck area. These were
screwed to the Blkhd stiffeners and to the blkhd to spread the load, they had
holes on top to install a 3/8” ss U-bolt which fitted through a hardwood cleat
.
The
purpose of these U-bolts was to attach the slings used for turning the boat
over. I reinstalled these U-bolts later permanently after the side decks were
fitted and they provide now an easy way to hook up to the lifting gear under
the shed roof to lift the boat onto its trailer.
The
anchor locker needs to be done at this stage if it is desired to build one in.
For this I built up the side faces of
the stem with western red cedar strips to fill the wedge shaped gap which would
be there after the topsides are fitted. I made small notches halfway along the
aft face of the stem from where 25x25mm cedar strips angled up to the outside
face of blkhd A at the sheer clamp. This was the support for the sloping locker
bottom. The reason the angled supports were of cedar is they need to be shaped
later to be flush against the topsides, use a batten to get this shaping right.
When
the boat is rightway up the sloping locker floor has its lowest point just
under the towing U-bolt in the stem and it slopes up aft to facilitate draining
of the locker.
As the
locker sides are the boats topsides it only remained to fit the locker back
which was up to the foredeck level just forward of the deck doubler here. Make
sure the mast tube has room aft of the anchor locker back!
The entire anchor locker was glassed with
10oz glass cloth to avoid damage by sharp anchor flukes later.
It is advantageous
to have this tube is available at this stage to install the bottom supports for
the mast tube. These would be much more difficult to fit later through the
opening in blkhd A if the topsides block side access.
If you
follow my philosophy of painting all inside surfaces don’t forget the forward
face of blkhd A, very difficult to paint here later.
Once
all vertical inside panels had been installed, painted and faired to the bottom
curve, the first layer of the bottom was fitted.
As mentioned earlier, these panels were
scarfed in place. To scarf the plywood edges I made a scarfing fence attachment
for my Hitachi power planer. The planer already had one transverse hole to hold
a fence, I made another hole on the other end of the planer to hold a fence
attached by two points which could not flex sideways. This fence is a length of
aluminium angle, 50x50x3mm and as long as the planer. The angle was located
with the horizontal side level to the planer bottom and the vertical side
facing away from the planer. The two rods to the fixing holes in the planer
body were attached at the fence by a fitting screwed to the aluminium angle which allowed to tilt and
lock this angle in place in relation to the planer bottom. By setting the angle
on a slight tilt (found by experiment how much) and running this angle against
a guide clamped to the plywood sheet, the planer , being held at an angle, took
a tapering bite into the ply. Repeated passes produced a perfect scarf join. Of
course this could also be done by using a hand plane but the power plane is
quicker and it allows the job to be done on the floor if the plywood sheet is supported by another one.
I
placed the first layer of the bottom with the sheets grain running fore and
aft. The middle of the hull is wider than the sheets but the CB case splits
most of this area in half anyway. On my boat all the first layer scarf joins
were located over a blkhd so that no joins were visible from the inside on my
bright finished cabin floor. This requires carefully juggling to avoid wastage.
The sheet forward of blkhd D is still too narrow to reach to the boat sides so
I scarfer triangular off cuts on there. These joins are under the battrey
lockers.
I used
8 sheets of 4x8’ marine ply for both layers, 12mm marine ply is expensive,
measure twice and cut once J.
The
panels were first installed dry with screws to the blkhds and chine logs and
weights on top and then all gluing areas marked off from inside, then glued on, one sheet at a time. It is
difficult to move these heavy sheets in place once the epoxy is applied, they
will slide off quicker than you can reach for the battery drill to drive the
screws home. I inserted some temporary eye bolts to suspend the sheet over the
desired location from the roof. Applying epoxy to the bulkheads and to the
underside of the hanging sheet was manageable, the sheet was then lowered in
place and screwed home.
If you
use the scarfing method of joining you need to start at the sheets on each side
of the CB trunk, the forward and aft scarfes on the same side, facing away from
each other. The feather edge of the scarf is always down, against the blkhd.
Then
work forward and aft alternately with the sheets scarfed on opposite sides,
take care to work out which side is scarfed as its very easy to get confused
here. Mark all scarf sides while
marking out the sheet outline cuts, then check them again before you
fire up the planer.
The
epoxy squeezed out along the scarf line on the blkhd needs to be carefully
cleaned up by the heat gun method to ensure the next sheet fits perfectly. Once
you have done the first scarf join the rest just become routine, its really not
difficult to join large panel segments this way.
I made
good use of the heavy lead ingots along the scarf gluing line to make sure it
fits without voids, its better to have a very slight hollow than a bump there
which would need to be belt sanded off later.
Once
all the first layer bottom panels were fitted I used the belt sander to trim
the plywood edge along the chine log to its bevel.
The
topside panels were next on the list, these were scarfed and fitted, one at a
time, as the bottom panels. Here it would have been too much wastage of plywood
to try to get all the scarf joins located over a blkhd. I started from aft and
the first join did coincide with a blkhd. The next one fell just short of blkhd
C. A stout , plastic covered, plank was screwed to the already fitted panel
inside at the scarf join to provide a
pressure area for the next panel on the feather edge. As usual, everything was
fitted dry first to drill the screw holes which held the panel to the chine
log. Another plastic covered plank on the outside sandwiched the scarf join and
these were screwed together to keep pressure on the scarf while the epoxy set.
In this
way all the topside panels were installed, now the hull really looked good.
The
chines were belt sanded to match the bottom plywood and the second layer of the
bottom followed, overlapping the topside edges.
This I installed with the plywood panel grain
lying across the hull, starting aft and working to the bow one panel at a time
was marked, cut out and fitted. The suspension method was again used to apply
the epoxy. There must be some screws, located and threaded partway, to lock the
panels and prevent their sliding off. The epoxy was spread with a notched
applicator with the bead directions at right angles on the hull and the
suspended panel. The sawhorses were handy there to make a plank walkway along
the hull to easily reach this area.
I also
used the extra heavy ballast slabs to press down the laminate, with the first
layer installed, the hull could take this extra weight. These panels did not
overlap the edges of the CB slot side panels as I later glued a hardwood strip
in place there to bury the edge grain of the plywood in this wear area.
The
hull was marked now with its waterline. To do this I drilled small holes at the
blkhd locations, on which the waterline had been marked previously, through the
topsides. Nails were pushed into these holes from the outside and a long batten
bent around this and the waterline marked onto the hull sides.
When
the double layer bottom was complete the chine edges were rounded off well but
the transom edge left square (makes less turbulence there).
Fill all
screw holes and check the entire hull surface for epoxy drips and lumps which
need to be removed before the glassing stage.
I
glassed the bottom with 10oz woven glass cloth. First the glass cloth was cut
and placed on the dry hull, it was smoothed and the ends fixed with short
pieces of masking tape. Then the epoxy was applied, pouring it from the mixing
container onto the glass and spread carefully with a plastic spreader until the
glass was roughly covered. Then I used a foam roller to toll it into the weave.
Try to apply not too much epoxy, just enough to fill the weave and so that the
white glass becomes transparent.
Next
came the topsides, one at a time. Spread the epoxy as above, making sure the
glass cloth does not slide about. It may be required to insert strategic
staples to stop the wetted out glass sliding off. Remove the staples when the
epoxy has cured.
On my
boat the outside ballast was attached now. There is a double layer of lead
slabs on each side, the lower layer had holes cast in where the bolts cast into
the upper layer passed through.
The lead slabs were placed in location and
the outline marked on the hull. A whack with a rawhide mallet easily formed the
lead to the bottom curve of the hull. As mentioned earlier, I kept the slab weight
to 50kg, this required 12 slabs for the ballast.
I since
removed the upper aftermost slab later so there are now only 10 lead slabs on
the outside of the hull bottom.
Flipping
the first layer over and aside, the marked area was sanded with 40 grit as was
the lead surface and butting area. The lead was covered with straight epoxy
which was sanded in wet and the hull also wetted out. Next a generous buttering
of fortified epoxy to both surfaces and the slabs were flipped back into
position. To move the heavy, epoxy coated, lead slabs it is advisable to devise
some kind of handles to grip the slabs. Some temporary nails kept the slabs
from sliding off until the epoxy cured.
Then
the holes for the bolts were drilled into the hull through the cast in holes in
the lower slab layer and the process repeated to epoxy on the top layer. Make
sure that there is a washer and nut placed on the bolts inside the hull to stop
the epoxy running out down there.
Faired
pieces of hardwood were epoxied ahead and aft of the lead ballast and any gaps
were filled and smoothed out.
Then I
glassed a very heavy weight triaxial glass tape, 150mm wide, around the chines
for the full length, the centre of the
hull bottom from the bow to the CB slot and over the faired lead ballast
skegs.
This
was for extra wear protection when the boat is on the trailer or while being
beached.
The
recess for the CB slot flaps was also routed out at this stage, making sure
this area received a very good, soak in, epoxy covering after. The opening for
the motor leg was cut out next and its lid finished.
With
the entire hull now glassed and after washing any amine blush thoroughly off
with water, the hull bottom up to the waterline was covered with an epoxy and
graphite powder mixture. Subsequent coats also had fairing compound added. This
was smoothed and faired with longboards as described below.
On the
topsides I rolled on another coat of epoxy to fill the weave. Then if there any
hollows or bumps they need to be filled with epoxy, thickened by filling
compound. Spread this with a notched applicator in a vertical direction. Do the
same to the hull bottom but also mix in graphite powder to keep the mixture
black. Make sure the ballast skegs and triaxial tape edges are faired in well
with this mixture.
Now the
longboarding. Begin sanding in a fore
and aft direction across the beads
until the sanding starts cutting into the plain epoxy coat, do not sand into
the glass layer.
This is
a very messy job, keep that vacuum cleaner busy and don’t forget the dust mask.
I wore disposable Tyvek overalls, they
lasted for a few sessions and are quite cheap.
Next
all the remaining grooves between the epoxy beads on the hull need to be filled
with epoxy fairing compound, applied with a straight edge applicator. Another
light sanding and she should be ready for undercoating. I made the mistake to
think that very slight dimples would be filled by the undercoat, this took too
many coats and lots of sanding. Better to get the hull as smooth as possible
with the epoxy and filling compound first!
With
the hull sides faired and undercoated, the bottom smooth with graphite filled
epoxy, the hull was now ready for the big moment of turning over.
Before
I did this I placed two stout 100x100mm logs along the ballast skegs and
levelled them carefully. Then I measured and glued on spacers to the logs to
follow the skeg curvature. After cross braces were fitted and the logs exact
position marked on the lead skegs with masking tape, they were removed and put
aside for now. These were used later for the hull to sit on and remain level
when she was turned over.
Two
lifting webbing straps from the winch contraption overhead were attached on one
side of the hull to the U-bolts fitted to the chainplates. The other two
straps, on the opposite side, were lashed to the U-bolts there and continued
under the hull to shackle to the U-bolts where the first straps terminated.
To
operate this, both winches (one at each side of the hull) were wound in to take
the weight of the hull. Wrap padding anywhere the webbing straps cross anything
sharp. Then all the supports to the building frame need to be removed to free
the hull.
IF YOU
USE THIS SYSTEM MAKE SURE YOUR LIFTING GEAR AND THE ROOF BEAMS ARE UP TO THE
TASK!
I
blocked the hull up with temporary logs across the building frame for extra
safety while I crawled under there to undo and remove all the blkhd supports.
When
all was clear the building frame too was dismantled and removed, keeping the
safety logs in place.
All the
lifting gear was double checked and the hull lifted off the logs a little by
each winch. I let it hang there over night to make sure all was OK to take the
weight!
Now,
one winch, on the side where the webbing was lashed to the U-bolts was used to
raise the hull a little. At the same time the winch on the other side of the
hull lowered it a little.
This
was continued, gradually turning the hull over while it was never more than a
few inches above the floor.
When
the hull was at 90 degrees the lashing mentioned earlier was removed, the hull
still being cradled and supported by the webbing attached to the other U-bolt.
All the weight of the ballast was now borne by the lowering winch and it
groaned accordingly.
THE
WINCH AND TACKLE MUST BE RATED FOR THE FULL WEIGHT OF THE HULL AND BALLAST, an
estimated 1200 kg at this stage in my case.
Both
winches were later used on the boat trailer, one for tilting it, the other to
retrieve the boat.
The
turning over continued in this fashion until she was rightway up. The hull was
raised a little to allow the prepared levelling logs to slide under the skegs
and lowered to rest there. There was no drama with this method of hull turning
over other than the alarming groaning noises from the winch (which I forgot to
grease).
The
hull was checked if it was level and secure (no rocking!) and the beer was
opened.
The
webbing spools for the lifting contraption under the roof were spaced to fit
the hull width so no crushing of the blkhds occurred, I temporarily reinforced
blkhd F with cross beams for extra security.
Now the fitout could begin in earnest, I
started with the Cockpit floor to have something to stand on while climbing
about the hull. Temporary planks made a step where the cockpit seats were.
As
before, all items were dry fitted, then removed and finished on their under /
insides to the final paint cover before epoxying them into place.
I
figured it would take me one year to finish the boat from there, it took nearly
two years in the end. Its tempting to cut corners and hurry on for the
launching while the inside of the boat is not finished. I believe in getting
this job done completely to enjoy the sailing later without seeing lots of
things which still need to be finished off in the boat all the time.
With the
cockpit seats and their locker lids done, the thwart installed, all the bunk
tops and their locker lids finished, the motor bracket operational and the tank shelf installed
there I tackled the inside shelfs.
For all
items abutting the hull sides I first glued those triangular cleats in place,
bevelled to the correct angle. Then I got a piece of scrap ply such as old door
skin or stiff cardboard and cut it roughly to shape. Then, holding this in
place against the hull side, I used one of the perspex disks, a pencil through
the hole in the centre and the disk rolling along the hull side while it was
kept flat against the scrap ply transferred the hull curve to the scrap ply.
After trimming this and checking for a good fit this shape was then transferred
onto the okoume plywood. In my boat most of the furniture is symmetrical on
both sides so I often could flip over the template and use it for the other
side.
In case
you are wondering how I clamped the triangular cleats to the hull while the
epoxy set, I used long battens to jam them in place from the opposite hull /
locker sides for this. Just remember this when you later crawl out of there and
don’t knock the battens off as I often did L.
When
all inside fittings were in place and I no longer needed to pass large items
into the boat the cabin sides and coaming were fitted. Do not cut out the windows first as the sides would then not bend fair
to the blkhds. These panels were also scarfed in situ, easier than trying to
get the long curved shape right in one piece. The cockpit roof was laminated
next, out of two layers of 4mm okoume plywood.
The
orientation and scarfing of the roof sections was done in similar fashion as on
the hull bottom with the difference that the entire inner layer was first
scarfed together on the floor and installed as one piece. The second layer was
vacuum bagged on. I’ll provide the details of this process to those who are
wishing to do it that way.
With
the cabin roof finished only the side decks remained off the boat, these were
deliberately left off until last as it was easier to install all the wiring now
into ducts screwed to the outside of the carlins. The centre cabin light had
its wiring run into a groove routed in the roof beam before installing the
cabin roof. The distribution panel and switch panel are in the small cubbies in
the forward face of blkhd E, the wiring to this goes up from the carlin duct
through the forward coaming void into the upper cubby space.
The
only place I could find to run the wiring out of sight from stbd to port was through a conduit that
passes under the outside companion step (this step is as deep as the angled add
on blkhd).
I also fitted a second conduit there to run
the water hose from the stbd tank to the pump on the port side. The water hoses
were run up under a ply cover aft of the blkhd E stiffener. The deck filler is
just above in the side deck.
All
this work needs to be considered while the boat still is in the skeleton stage,
once you have covered up here its very difficult to cut the required openings.
Before
fitting the side decks, which were scarfed in place as usual with the scarfes
at blkhd locations, I glued on an outed sheer clamp as an afterthought . This
was made from scarfed lengths of douglas fir, about 20x50mm, and clamped to the
inner sheer clamp while the glue set. After this was sanded to follow the sheer
line the side decks were installed.
Then
I used a power plane to shave off the angled outer side of this outer sheer
clamp to make it vertical. A vertical surface is much tougher than an angled
one for the inevitable bumps when coming alongside. Removable teak rub rails,
which were scarfed up from 4 sections, was screwed to this. The rub rail
continues across the transom for visual effects.
The
boats maximum beam was increased by this addition to 2.5m, the legal maximum
towing width here. It also gives a slightly wider side deck to fit the last
item there, a trapezoid shape toe rail. This is in 4 sections, each terminating
at the stanchion bases to prevent water pooling there.
Now the
hull was pretty much finished apart from some teak trim here and there and the
painting.
I spent
ages on filling and sanding with high build primer and it was really worth the
effort, most people seeing the boat were thinking she was built of fibreglass.
The
final finish is only as good as the surface beneath it and any hollows are
magnified by the gloss paint.
Using
two part paint would give a tougher finish but these paints really need a
professional with a spray gun. My boat
looks pretty good with the one pot polyurethane paint, its also easier
to touch up scratches on this finish later.
I
painted the cabin top with an off white colour in the slightly stippled finish produced
by the foam roller. This hid rather than highlight the small imperfections
there, fairing the highly chambered surface was much more tricky than the hull
was.
The
side decks were coated with non slip paint of light grey colour, the masking
around the fittings is a bit tedious. Rather than trying to curve masking tape
around the small radius at the deck fittings I used the clear film as used for
book covers and such. The shapes were cut with scissors and the film stuck to
the appropriate place, it proved successful and no paint seeped under its
edges.
There
are some bright finished teak trims on the outside of my boat, I kept those to
a minimum to keep the varnishing maintenance low. The teak slats on the seat
and cockpit floor were left as is and
they wear to a pleasing grey finish.
Initially
I planned to just paint the cockpit and had covered all areas with glass cloth
but this finish looked a bit too plain and slippery there, hence the addition
of the slats for a touch of class.
When
bolting items to the cockpit or deck I always drilled the hole one size up and
coated it with epoxy along its length to waterproof the wood. The item then was
also bedded with sikaflex and I expect no leaks on my boat (so far so good).
The
boat was now nearly finished, I fitted the motor which had to be lowered onto
the bracket tracks by a chain hoist, it’s a tight fit in there.
The
hull was the raised as high as the lifting gear allowed, some sturdy steel
trestles placed under the lead skegs for safety, and the centreboards were
installed. They were lifted into place by their own tackles, I made large,
thin, teflon disks to fit on each side and it was a tricky operation to raise
the boards into the CB case while keeping the teflon disks lined up.
All
that remained was to roll the trailer under her and lower the boat. The home
made trailer looked a lot better than it functioned in its original design, two
major modifications later this problem was finally solved. I now can launch and
retrieve the boat single handed as well as sailing her that way.
She
turned out great, much better than I had hoped at the beginning.
Keep in
mind that I wrote the above from memory after the boat had been finished and
launched for 10 months. If you find something confusing please contact me and I
may be able to explain it better.
Have
fun building your boat.
-Klaus-